Risk Assessment and Analysis in Civil Construction Projects Using ANP

Volume 6, Issue 7 - Serial Number 65
September 2024
Pages 25-39

Document Type : Research Article

Authors

1 Civil engineering, construction engineering and management, Islamic Azad University, Shiraz Branch, Shiraz, Iran

2 1- Department of Civil engineering, Shiraz Branch, Islamic Azad University, Shiraz, Iran

Abstract
One of the goals of knowledge of construction management is to identify the unforeseen factors and situations in the way of implementing projects in order to provide effective plans for dealing with potential risks and project risks. Risk assessment is one of the most important factors in risk management and research indicates the need to use risk assessment to achieve success in construction projects. The aim of this study is to identify the types of risks in constructions projects based on the PMBOK, analysis, ranking and priority of risks using ANP method in order to improve the technical, qualitative and economic aspects of constructions projects. this research is in search of a suitable model that can use risk management and its methods in order to implement the economic and technical implementation of civil engineering projects. At first, 40 risks were identified in the context of 8 groups of risk factors through library studies and interviews, then by questionnaire and their analysis, were finally identified and ranked as the most important risks in constructions projects. Also, experts’ and experienced managers’ expertise in constructions activities was duly consulted to identify and prioritize the risks, and for the analysis of information, ANP and Super Decision software were used. Finally, it was found that the risk of delay in case of situations, adjustments and other costs to the contractor from the risk group of employers is the most important risk.

Keywords

Subjects
Akbarzadeh Bengar, H. & Mahmoudi, B. (2017). Prioritize the risks of the municipal sewage
construction project. The 1 st International Conference on Recent Progresses in Civil Engineering,
Shomal University, Amol, Mazandaran, Iran. (In Persian)
doi:10.1016/j.aej.2018.10.018
Dorri, B; Hamzaei, A. (2010). Determining risk response strategy in risk management by ANP
technique (case study: North Azadegan oil field development project). (pp. 75-92). Tehran: Industrial
Management.
Eskander, R. F. A. (2018). Risk assessment influencing factors for Arabian construction projects using
analytic hierarchy process. Alexandria Engineering Journal, 57(4), 4207-4218.
Haj Shirmohammadi, A. (2015). Project management and control. Isfahan: Arkan Danesh
Publications.
Nazari,A; Forsatkar,A. (2008). Risk management in projects. Tehran: Publications of Management
and Planning Organization.
PMBOK. (2004). A Guide To The Project Management Body Of Knowledge(PMBOK Guide). usa:
project management institute inc.
Saati, T. (2004). Fundamentals of the analytic network process - Dependence and feedback in
decision-making with a single network. Journal of Systems Science and Systems Engineering ,1-35.
Sheikh, M. (2005). Investigating the application of risk management in power plant projects. Tehran:
Faculty of Arts, Tarbiat Modares University.
Steffen, B. (2018). The importance of project finance for renewable energy projects. Energy
Economics, 69, 280-294.
Tasa, O., Gulabchi , M. & Ravanshadnia, M. (2023). Evaluating the Response to Risks in Complex
Construction Projects Using the Fuzzy TOPSIS Method. Industrial management journal, 15(2), 335-364
doi:10.22059/imj.2023.352751.1008010 (in Persian)
Valipour, A. e.(2013). Analytic Network Process (ANP) to Risk Assessment of Gas Refinery EPC
Projects in Iran . journal of Applied Sciences Research, (3)9 :1359-1365.
Wu, Y., Zhang, B., Xu, C. & Li, L. (2018). Site selection decision framework using fuzzy ANPVIKOR
for large commercial rooftop PV system based on sustainability perspective. Sustainable Cities
and Society, 40, 454-470.
Yang, Y. P. O., Shieh, H. M. & Tzeng, G. H.( 2013). A VIKOR technique based on DEMATEL and
ANP for information security risk control assessment. Information Sciences, 232, 482-500.
Yazdani, M. (2007). Investigating the time risks of constructing intra-urban highways in Tehran.
Tehran: Shahid Beheshti University.
  • Receive Date 04 April 2024
  • Revise Date 09 May 2024
  • Accept Date 12 May 2024
  • First Publish Date 12 May 2024
  • Publish Date 22 September 2024