An Integrated Structural Equation Modeling and Random Forest Approach for Identifying and Predicting Temporal Constraints in Construction Project Performance

Volume 7, Issue 8 - Serial Number 78
November 2025
Pages 49-68

Document Type : Research Article

Authors

1 Asistant Professor, Faculty of Engineering, Hakim Sabzevari University, Sabzevar, Iran

2 M.Sc.Student, Faculty of Engineering, Hakim Sabzevari University, Sabzevar, Iran

Abstract
Temporal constraints are among the most significant challenges in construction project management, often causing schedule delays, cost escalations, quality decline, and dissatisfaction among stakeholders. This study presents an innovative integrated framework combining Structural Equation Modeling (SEM) and Machine Learning (Random Forest) to identify and predict the key factors affecting timely performance in construction projects. SEM results reveal that six critical factors—environmental conditions, stakeholders, regulations, policies, management, and traditional beliefs—have significant negative impacts on project performance. Among these, policies and management exhibit the strongest effects. The SEM model explains 67% of the variance in project outcomes, highlighting its explanatory power.

Following this, the Random Forest algorithm was employed to predict project timeliness, achieving an accuracy exceeding 87%, thus validating the importance of the identified factors. Feature importance analysis from the Random Forest model corroborates the findings from SEM, emphasizing the dominant role of policies, management, and regulations. This combined approach offers both a causal understanding and a powerful predictive capability, enabling early-stage identification of potential delays and risk factors.

The methodological novelty of this research lies in integrating SEM’s causal modeling with the predictive strength of machine learning, providing a comprehensive tool for construction project analysis. The findings hold practical implications for project managers and policymakers, especially in contexts like Iran where managerial and institutional challenges prevail. This framework supports data-driven decision-making and risk mitigation, ultimately aiming to improve the efficiency and success rates of construction projects.

Keywords

Subjects
Adedokun, O. A., et al. (2023). Risk factors and their impact on project success: Evidence
from educational building projects. Journal of Engineering, Design and Technology, 21(6),
1901–1924.
Breiman, L. (2001). Random forests. Machine Learning, 45(1), 5–32.
Buildings. (2025). Analyzing delay factors in construction projects using SEM. Buildings,
15(2), 678.
Egwim, E., et al. (2021). Machine learning models for predicting delays in construction
projects. Automation in Construction, 124, 103556.
Hair, J. F., Hult, G. T. M., Ringle, C. M., & Sarstedt, M. (2021). A primer on partial least
squares structural equation modeling (PLS-SEM) (3rd ed.). Sage.
Ingle, P. V., & Mahesh, G. (2022). Construction project performance areas for Indian
construction projects. International Journal of Construction Management, 22(8), 1443–
1454.
Misnan, M. S., Ismail, M. Z., & Yan, T. J. (2024). Challenges and prospects in sustainable
project management. International Journal of Research and Innovation in Social Science,
8(2), 1997–2011.
Prokhorenkova, L., Gusev, G., Vorobev, A., Dorogush, A. V., & Gulin, A. (2018).
CatBoost: Unbiased boosting with categorical features. Advances in Neural Information
Processing Systems, 31, 6638–6648.
Rady, M., et al. (2023). Constraint factors affecting project performance: A PLS-SEM
approach. Mathematics, 11(3), 734.
Sarstedt, M., Ringle, C. M., & Hair, J. F. (2022). PLS-SEM: Indeed a silver bullet. Journal
of Business Research, 144, 311–320.
Shmueli, G., Ray, S., Estrada, J., & Chatla, S. B. (2019). The PLS predict algorithm:
Prediction-oriented model evaluation in PLS-SEM. Information Systems Journal, 29(1),
219–238.
Shmueli, G., Sarstedt, M., Hair, J. F., Cheah, J.-H., Ting, H., Vaithilingam, S., & Ringle, C.
M. (2019). Predictive model assessment in PLS-SEM: Guidelines for using PLSpredict.
European Journal of Marketing, 53(11), 2322–2347.
Yaseen, Z. M., et al. (2020). Delay prediction in construction projects using hybrid random
forest and genetic algorithm. Sustainability, 12(5), 1830.
Zhang, X., et al. (2020). Predicting construction project delay using random forest. Journal
of Construction Engineering and Management, 146(5), 04020032.
  • Receive Date 28 June 2025
  • Revise Date 18 July 2025
  • Accept Date 19 August 2025
  • First Publish Date 19 August 2025
  • Publish Date 23 October 2025