INTEGRATED TIME AND COST CONTROL FRAMEWORK FOR CONSTRUCTION PROJECTS BASED ON EARNED VALUE MANAGEMENT: A CASE STUDY OF THE NATIONAL HOUSING PROJECT IN ABHAR

10.22034/cpj.2026.610543.1485

Document Type : Research Article

Authors

Department of Civil Engineering, Faculty of Engineering, Saeb Institute of Higher Education, Abhar, Iran.

Abstract
Construction projects are frequently exposed to simultaneous schedule and cost deviations, while conventional monitoring may not reveal the relationship between planned work, physical progress and actual expenditure. This study develops and evaluates an integrated time–cost control framework based on Earned Value Management (EVM) for a National Housing project in Abhar, Iran. The research is applied in purpose, descriptive–analytical in nature, and based on a case-study design. The project comprises three residential blocks (M6, M7 and M8), which are treated as one integrated control unit. Schedule, reported physical progress and cumulative cost information were organized using Microsoft Project and Excel. At the principal control point, the total budget (BAC) is 25 billion toman, Planned Value (PV) is 10.25 billion toman, Earned Value (EV) is 6.125 billion toman, and Actual Cost (AC) is 7.35 billion toman. The resulting SPI is approximately 0.60 and CPI is approximately 0.83, indicating simultaneous schedule and cost underperformance. A transparent what-if corrective scenario is then evaluated by targeting SPI=0.85 and CPI=0.95 while keeping the baseline PV unchanged; the resulting EV and AC are approximately 8.71 and 9.17 billion toman, respectively. Forecasts are presented only with explicit formulas and assumptions. The contribution of the study is not a new EVM formula, but an implementable control cycle linking baseline planning, progress measurement, EVM diagnosis, qualitative cause analysis, and corrective decision-making for a multi-block residential project. Because the original detailed EVM worksheet was unavailable during reconstruction, the reported aggregate control-point progress is retained as the primary EV basis and its provenance is explicitly disclosed.

Keywords

Subjects
1. Aliverdi, R., Moslemi Naeni, L., & Salehipour, A. (2013). Monitoring project duration and cost in a construction project by applying statistical quality control charts. International Journal of Project Management, 31(3), 411–423.
2. Amini, M., Nohani, E., & Noorolah Dezfouli, M. H. (2024). Identification and ranking of factors influencing the non-implementation of risk management in small-scale civil projects (case study: Civil projects in the city of Abadan). Civil and Project Journal, 5(12), 11–28. https://doi.org/10.22034/cpj.2024.434589.1252 [persian]
3. Ateş, B., & Eirgash, M. A. (2025). Proactive and data-driven decision-making using earned value analysis in infrastructure projects. Buildings, 15(14), 2388.
https://doi.org/10.3390/buildings15142388
4. Barkhordari Dashtkhaki, A., & Tabatabaei Mirhosseini, R. (2025). Identification and prioritization of influential criteria in achieving the program scheduling in construction projects. Civil and Project Journal, 7(4), 11–28. [Persian]
5. Duc, N. A. (2025). Risk-based earned value management with cost–time mutual effect to enhance construction forecasts and management. Journal of Science and Technology in Civil Engineering, 19(2), 62–77. https://doi.org/10.31814/stce.huce2025-19(2)-05
6. Elsaid, M., Nassar, K., Alqahtani, F. K., & Abotaleb, I. (2025). Comparative analysis of earned value management techniques in construction projects. Scientific Reports, 15, 23606. https://doi.org/10.1038/s41598-025-05834-z
7. Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.
8. Kim, B.-C., Kim, H.-J., & Park, H.-S. (2015). Integrated CO2, cost, and schedule management system for building construction projects using the earned value management theory. Journal of Cleaner Production, 103, 275–285.
https://doi.org/10.1016/j.jclepro.2014.05.031
9. Mostofi, F., Tokdemir, O. B., & Toğan, V. (2026). Bidirectional spatio-temporal networks for predicting cost performance in construction using deep learning extension of earned value management. Automation in Construction, 181, 106597.
https://doi.org/10.1016/j.autcon.2025.106597
10. Ngo, K. A., Lucko, G., & Ballesteros-Pérez, P. (2022). Continuous earned value management with singularity functions for comprehensive project performance tracking and forecasting. Automation in Construction, 143, 104583.
https://doi.org/10.1016/j.autcon.2022.104583
11. Ottaviani, F. M., Ballesteros-Pérez, P., & Narbaev, T. (2025). Automated machine learning pipeline for robust project cost and duration forecasting. Automation in Construction, 178, 106426. https://doi.org/10.1016/j.autcon.2025.106426
12. Panquet, Q., Bourgault, M., Pellerin, R., Danjou, C., & Perrier, N. (2024). A process-improvement method for implementing earned value–based project management in organizations. Journal of Construction Engineering and Management, 150(12).
https://doi.org/10.1061/JCEMD4.COENG-15041
13. Project Management Institute. (2019). The standard for earned value management.
14. Rostampour, D., & Mazhari, M. Y. (2024). Evaluation of the effect of project management based on knowledge on risk management in Mehr housing projects of Sanandaj. Civil and Project Journal, 6(10), 11–26. [Persian]
15. Sruthi, M. D., & Aravindan, A. (2020). Application of earned value management in residential building project. Materials Today: Proceedings, 33, 524–532.
https://doi.org/10.1016/j.matpr.2020.05.210
16. Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), 289–302. https://doi.org/10.1016/j.ijproman.2005.10.004
17.Yang, J. B., & Lai, T. H. (2024). Selecting EVM, ESM and EDM(t) for managing construction project schedule. Engineering, Construction and Architectural Management, 31(12), 4988–5006.
  • Receive Date 01 October 2026
  • Revise Date 17 October 2026
  • Accept Date 17 November 2026
  • First Publish Date 17 November 2026
  • Publish Date 21 April 2027