Golabchi, Talkhabi; Hadi, Parchami; Jalal, Bemanian. (2014). Development and Analysis of a
Claims Package Model in Non-Industrial Design and Construction Projects in Iran, Management
Research in Iran, 18(4(
Golshani Manesh, Morteza; Golshani Manesh, Maryam. (2017). Studying the effect of claim
management and time and cost management in key road, pavement and bridge projects, 7th
International Conference on Sustainable Development and Urban Development, Isfahan, Institute of
Advanced Studies - Dortmund University of Technology, Germany - General Directorate of Roads
and Urban Development of Isfahan Province - Isfahan Municipality and the specialized parent
company of Iran's Urban Development and Improvement.
Hosseinzadeh Bahreini, Mehdi. (2015). Claims Management in Civil Projects, Second National
Conference on Construction and Project Management, Tehran, Ala-od-Dowleh Semnani Institute of
Higher Education.
Jabal Ameli, Mohammad Saeed; Nouri, Siamak; Bayisteh, Ali. (2008). Claims Management Plan
in Civil Projects (Case Study), Fourth International Conference on Project Management, Tehran,
Ariana Research Group.
Rosati, Shahram; Khodai, Leila; Mokhtari, Davud; Rezatab, Khadija; Khodai, Fatemeh. (2015).
Application of Analytical Network (ANP) in Investigating Landslide Potential in the Area of Qaleh-
Chay Dam Axis and Reservoir, Natural Environmental Hazards.
Akbari, A., Feili, A., & Dashtipour, M. (2022). Identifying and prioritizing arising claim's factors
by the combined approach of DEMATEL and ANP method (case study: urban development and
civil organization of shiraz municipality projects). Journal of Soft Computing in Civil
Engineering, 6(1), 46-65.
Alaghbari, W. E., Kadir, M. R. A., & Salim, A. (2007). The significant factors causing delay of
building construction projects in Malaysia. Engineering, Construction and Architectural
Management.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International
journal of project management, 24(4), 349-357.
Azar, A., & Rajabzadeh, A. (2010). Applied decision making MADM approach. Tehran.
Badenfelt, U. (2008). The selection of sharing ratios in target cost contracts. Engineering,
Construction and Architectural Management, 15(1), 54-65.
Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement
contracts. Rand journal of Economics, 387-407.
Bakhary, N. A., Adnan, H., & Ibrahim, A. (2017). A study of construction claim management
problems in Malaysia. Procedia economics and finance, 23, 63-70.
Berends, T. C. (2000). Cost plus incentive fee contracting—Experiences and
structuring. International Journal of Project Management, 18(3), 165-171.
Bresnen, M., & Marshall, N. (2000). Motivation, commitment and the use of incentives in
partnerships and alliances. Construction Management and Economics, 18(5), 587-598.
Broome, J., & Perry, J. (2002). How practitioners set share fractions in target cost contracts.
International Journal of Project Management, 20(1), 59-66.
Chan, D. M., Chan, A. P., Lam, P. T., Lam, E. W., & Wong, J. M. (2007). Evaluating guaranteed
maximum price and target cost contracting strategies in Hong Kong construction industry. Journal
of Financial Management of Property and Construction, 12(3), 139-150.
Chan, D. W., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in
Hong Kong construction projects. International Journal of project management, 15(1), 55-63
Civil and Project Journal, 2025, 7(8), 34-48
https://doi.org/10.22034/cpj.2025.536227.1387
47
Chan, D. W., Chan, A. P., Lam, T. I. P., & Chan, H. L. (2010). Exploring the key risks and risk
mitigation measures for guaranteed maximum price and target cost contracts in construction.
Construction law journal.
DOE, U. (2005). International Energy Outlook 2005. DOE/EIA, 484.
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in
Indian construction projects. International journal of project management, 30(4), 479-489.
Easton, G. R. (1989). ‘‘Construction claims.’’ Dept. of Civ. Engrg.
ebrahimi, s. n., & akbari, m. (2017). identification, assessment and management of the risks in oil
and gas design-build (db) contract, and their impacts on preventing claims and disputes.
Eisenhardt, K. M. (1989). Making fast strategic decisions in high-velocity environments.
Academy of Management journal, 32(3), 543-576.
Fenn P, Lowe D, Speck C. (1997). Conflict and dispute in construction. Constr Manage Econ.
15(6):513–518.
Finsen, E. & Povey, A. (2005). The Building Contract: A commentary on the JBCC Agreements.
(2nd ed). Cape Town: Juta … The Mediation Process Practical: strategie for resolving conflict. San
Francisco: Jossey-Bass.
Fuller, G. W. (1920). Cost Plus Contracts for Water Works Construction. Journal (American
Water Works Association), 7(5), 683-692.
Gordon, C. M. (1994). Choosing appropriate construction contracting method. Journal of
construction engineering and management, 120(1), 196-210.
Goyer, P. F., Andreason, P. J., Semple, W. E., Clayton, A. H., King, A. C., Compton-Toth, B. A.,
... & Cohen, R. M. (1994). Positron-emission tomography and personality disorders.
Neuropsychopharmacology, 10(1), 21-28.
Hosseinian, S. M., & Carmichael, D. G. (2014). An optimal target cost contract with a risk neutral
owner. Engineering, Construction and Architectural Management.
Jer Yuen, T., & Shaheen Majid, M. (2007). Knowledge‐sharing patterns of undergraduate students
in Singapore. Library Review, 56(6), 485-494.
Moavenzadeh, F., & Rossow, J. (1976). Risks and risk analysis in construction management. In
Proceeding of the CIB W (Vol. 65).
Morris, P.W.G., Pinto, J.K., )2007(. The Wiley Guide to Project Technology, Supply Chain, and
Procurement Management (The Wiley Guides to the Management of Projects). John Wiley and
Sons, Inc., Hoboken, New Jersey.
Motiar Rahman, M., & Kumaraswamy, M. M. (2002). Risk management trends in the construction
industry: moving towards joint risk management. Engineering, Construction and Architectural
Management, 9(2), 131-151.
Müller, R., & Turner, J. R. (2005). The impact of principal–agent relationship and contract type on
communication between project owner and manager. International Journal of Project
Management, 23(5), 398-403.
Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: traditional contracts.
International journal of project management, 20(1), 67-73.
Porter, C. E. (1981). Risk allowance in construction contracts. Unpublished MSc. project report.
Rahman MM, and Kumaraswamy MM. (2002). “Risk management trendsin the construction
industry: moving towards joint risk management”, Journal of Engineering Construction and
Architectural Management; 9(2):131–51.
Raz, T., Shenhar, A. J., & Dvir, D. (2002). Risk management, project success, and technological
uncertainty. R&D Management, 32(2), 101-109.
Rose, K. H. (2008). Book Review: Construction Extension to the PMBOK® Guide Third Edition.
Royer, P. S. (2000). Risk management: The undiscovered dimension of project management.
Project Management Journal, 31(1), 6-13
Saaty, T. L. (1996). Decision making with dependence and feedback: The analytic network
process (Vol. 4922, No. 2). Pittsburgh: RWS publications.
Saaty, T. L. (2008). Decision making with the analytic hierarchy process. International journal of
services sciences, 1(1), 83-98.
Civil and Project Journal, 2025, 7(8), 34-48
https://doi.org/10.22034/cpj.2025.536227.1387
48
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction
industry. International Journal of project management, 25(5), 517-526.
Wang, S., & Noe, R. A. (2010). Knowledge sharing: A review and directions for future
research. Human resource management review, 20(2), 115-131.
Ward, S. C., & Chapman, C. B. (1995). Risk-management perspective on the project lifecycle.
International Journal of Project Management, 13(3), 145-149.
Willem, A., & Buelens, M. (2009). Knowledge sharing in inter-unit cooperative episodes: The
impact of organizational structure dimensions. International journal of information
management, 29(2), 151-160.
Williams, T., Williams, M., & Ryall, P. (2013). Target cost contracts: adopting innovative
incentive mechanisms to improve the project delivery process [J]. Management, 759, 768.
Wu, W. Q., Xu, Y. F., Rao, H. S., Su, C. Y., & Kuang, D. B. (2014). Multistack integration of
three-dimensional hyperbranched anatase titania architectures for high-efficiency dye-sensitized
solar cells. Journal of the American Chemical Society, 136(17), 6437-6445.
Yahya, S., & Goh, W. K. (2002). Managing human resources toward achieving knowledge
management. Journal of knowledge management, 6(5), 457-468.
yusri, s. n. f. b. m. (2023) overcoming causes of claim disputes in construction projects: a dematel
based model.
Zineldin, M. (2006). The royalty of loyalty: CRM, quality and retention. Journal of consumer
marketing.